2021 Countywide Pavement Resurfacing
May to October 2021
Countywide
Investment: $3.5 million – County, $5.5 million – Townships, $1 million – OPWC
Asphalt resurfacing, micro-surfacing, chip sealing, crack sealing, berm repair, pavement marking and other work on various county and township roads throughout Delaware County. See the Delaware County 2021 Paving Guide.
East Powell Road, Phase 2
June 2020 to October 2021
Orange Twp.
Investment: $8.6 million – County Road & Bridge Funds
Widening of East Powell Road to 3 lanes between South Old State and Bale Kenyon. Sequenced road closures from east to west with next closure from Walker Wood Blvd. to I-71 beginning in April. Future closures between Tahoma St. and Walker Woods followed by Old State to Tahoma St. Overall project completion in October 2021.
Hyatts/Shanahan & US 23 Intersection
Sep 2020 to June 2021
Orange Twp.
Investment: $3.0 million – County Road & Bridge Funds
Widening of Hyatts Road and Shanahan Road approaches to US 23 for new turn lanes. Project also includes construction of sanitary sewers and a new sanitary pump station. Closure of Hyatts Road resumes in April lasting for about 6 weeks.
East Orange Road Improvements, Phase 2
Aug. 2020 to Nov. 2021
Orange Twp.
Investment: $2.5 million – Orange Twp, $500,000 – OPWC
Orange Township project to widen Orange Road to 5 lanes from the U.S. Post Office to just east of Green Meadows Drive and add 3 new traffic signals at Highfield, Green Meadows and Blue Holly Drive. Sequenced road closures between North Central and Green Meadows beginning in May 2021.
Worthington & Africa Road Intersection
Oct. 2020 to June 2022
Orange/Genoa Twps.
Investment: $6.0 million – County
Road & Bridge Widening of Worthington Road with 2 lanes in each direction through the intersection, and new turn lanes on Africa Road. Also widening for a 3-lane section on Worthington Road north to the Highland Lakes Ave. and cutting of hills to improve sight distance. 6 month closure to southbound traffic on Worthington Road beginning spring 2021 (northbound maintained) followed by short-term closures of Africa Road.
Sawmill Parkway and Hyatts Crossing Intersection
May to June 2021
Liberty Twp.
Investment: $125,000 – Developer; $125,000 – County
Addition of left turn lanes on Sawmill Parkway at Hyatts Crossing serving the new development to the west and the new county salt storage outpost on the east. Lane restrictions in each direction for approximately 3 weeks.